Sewerage and Water Board
New Orleans labels six kinds of pipe, and the replacement is free as funding allows
SWBNO's map, last updated March 2026, separates verified lead from assumed lead. The replacement program is free to the owner while funding lasts, and the utility prints a finish date of December 31, 2037.
Last verified 2026-11-21 against the utility, state, or EPA pages linked at the bottom. Figures move. The official page wins if this one is behind.
Assumed lead is not the same as verified lead
Search your service address on SWBNO's map. The pop-up covers the public side and the private side. The lead awareness page says the map was last updated in March 2026. Verified lead, verified non-lead, and galvanized mean the utility has a record. Galvanized lines are scheduled for replacement because they can hold lead particles.
The unknown labels are a model, not a shovel. Unknown means there was not enough data to model the line. Assumed lead means the model puts the chance of lead at 80 percent or higher. Assumed non-lead means 20 percent or lower. SWBNO says it is scheduling inspections to confirm all of those. The pages we read do not give a citywide total for any of the six labels. The map is the inventory.
Search the service address. The pop-up shows the public side and the private side. The lead awareness page says the map was last updated in March 2026. Labels include verified lead, verified non-lead, galvanized, unknown, assumed lead (the model says 80 percent or higher), and assumed non-lead (20 percent or lower).
Sign the right-of-entry, then wait out the funding
The replacement page says the goal is to remove lead, and that federal rules require the work done by December 31, 2037. CDM Smith manages the program. Only the owner can sign the right-of-entry form. Renters hand it to the landlord. It can go back online, to LSLR@swbno.org, or by mail to the Poydras Street address on the form.
A canvasser comes first, looks at where the pipe enters if it is visible, and collects the form. Then a small-dig inspection uses holes no bigger than two feet by two feet, mostly near the meter. If the line is lead, on either side, the contractor replaces it. The page says this is free as funding allows. Interior plumbing is not included. From the first visit to the replacement can take a year or more.
Two SWBNO pages describe the private-side money differently, and both were up when we checked. The awareness page says the utility is working on a legal path to spend public funds on private property. The replacement page says Constitutional Amendment 7 and a favorable Attorney General opinion already allow it, and that $152 million is currently available through the State Revolving Fund for the first years of the program. Later neighborhoods still need more money. If someone quotes you a price, ask which of those two pages they are reading.
- Program
- Lead service line replacement, free as funding allows
- Who pays
- SWBNO, for lead lines found in the program, public and private, while funding holds
- What the customer pays
- No cost to the property owner for a program replacement, as funding allows. The awareness page still describes private-side funding as a legal path being finished. The replacement page says Constitutional Amendment 7 and an Attorney General opinion already allow public funds on private property.
- Timing
- The replacement page says federal rules require the work to be finished by December 31, 2037. The awareness page says that starting in 2027, lead on both sides of the line has to be replaced in full, including the private side. After a visit, inspection and replacement can take a year or more.
A pitcher, six months of cartridges, and the street put back
After a replacement, SWBNO says you get flushing steps, a filter with six months of cartridges, and a follow-up water test offered under the federal rules. Pavement is supposed to be drivable the same day. Full restoration, including watered sod and the walks or driveway they disturbed, is within 45 days. The contractor, not a second company, does that restoration.
After a replacement, SWBNO provides a filter pitcher with six months of cartridges and offers a follow-up water test, along with flushing steps.
2027 is when full replacement becomes mandatory on their page
The awareness page says that starting in 2027, if lead is on both sides of the line, the entire line including the private side has to be replaced under the Lead and Copper Rule Improvements. That lines up with EPA's compliance date of November 1, 2027. The replacement page's finish line is December 31, 2037. EPA's fact sheet says within 10 years and does not, in the sheet we used, print that December date. SWBNO does. We are quoting SWBNO for the calendar day and EPA for the 10-year structure.
The industry case over the federal rule was argued on September 30, 2026. The right-of-entry form does not wait on that case. If you want the free inspection, the owner signs it.
Dates in this section follow EPA's October 2024 fact sheets, which are listed on the method page: an initial inventory on October 16, 2024, Lead and Copper Rule Improvements compliance on November 1, 2027, and full replacement within 10 years with the first rate check on December 31, 2030. A longer schedule is available only if a 10-year pace would mean more than 39 replacements per 1,000 service connections a year, and the state still has to call that pace the fastest feasible. The American Water Works Association sued over the rule (D.C. Circuit No. 24-1376). NRDC, which is in the case, says argument was held on September 30, 2026, EPA defended the rule, and a decision is likely months after argument. The dates on this page are the ones EPA published in October 2024.
If your water bill is from Sewerage and Water Board of New Orleans
- Search the March 2026 map and read both sides. Assumed lead is a model result, not a dug-up confirmation.
- If you are the owner, sign the right-of-entry form so a crew can inspect and, if needed, replace the line.
- Treat the price as no cost while the current funding covers your neighborhood. The utility says later years still need more money.
- Keep the pitcher and use the cartridges for the six months SWBNO supplies.
Open the lookup tool Compare what customers pay Print the next steps
Guides to read with the New Orleans record
- How to check your utility's service line inventory for your address
- What to expect when your lead line is replaced
- Filters while waiting for lead pipe replacement
- Renters and lead service lines
Other utilities checked on 2026-11-21: Colorado, Illinois, Wisconsin, New York, Pennsylvania, Michigan, Rhode Island, Minnesota, Florida, Ohio, Maryland, Washington.
Sources
- SWBNO, Lead Awareness, including the map legend and the March 2026 update note
- SWBNO service line material inventory map
- SWBNO, inspection and replacement, right-of-entry, cost, and filters
- EPA fact sheet: 2021 LCRR requirements retained, and LCRI compliance dates (October 2024)
- EPA fact sheet: calculating service line replacements (October 2024)
- EPA fact sheet: service-line inventory and replacement (October 2024)
- EPA FAQ for states and public water systems on the final LCRI (October 2024)
- NRDC case page: American Water Works Association v. EPA, updated September 30, 2026